Southeast Coast Sewarage & Drainage Project, Ayia Napa

The project consists of 42km of sewer, 37km irrigation and 11km of force main. The excavation works involved were approximately 108,000m3 at a maximum depth of 6 meters. 80,000m3 of asphalt reinstatement were required and 2500 house connections. The pipe laying included various types of pipes with sizes ranging from 50mm to 710mm. The project included the purchase and supply of all materials, complete construction, installation and testing of sanitary sewers, sewer force mains, complete reinstatement of the construction areas and all other associated works.